Close Gallery
F. Rodriguez, center.
Zoom Picture

SANTO DOMINGO.- Just while Dominicans were minding the presidential transition process , ex canals and dams agency (Indrhi) director Frank Rodriguez was preparing to sign contracts worth millions, reports diariolibre.com.

It said at least two of them with the same person, Angel Rondon Rijo, whose actions in the country has been questioned, and have been even brought to trial.

Right on 9 July the head Indrhi signed a contract with Consultoress & Contratistas (Conamsa), represented by Rondón, worth more than RD$61.0 million, for a canal at the Camu River, La Vega, and the construction of retaining walls at Montellano, Puerto Plata, in the areas of El Tamarindo, La Policia, Ls Mangos, Los Perez and Buen Pan

 The outlets reports that as part of the agreement the agency had to advance amount of 12 percent of the contract value of RD$61.3 million, or RD$12.2 million. Under the agreement, Conamsa was to conclude the work within 12 months.

 Just nine days after signing that agreement, the Indrhi signed another contract with the same company and its representative, this time for RD$19.5 million.

The works were a retaining wall at the Maimon riverbank, in Laguna Nisibón and the repairs to the dike La Mina de Oro, in the same area. Of the total amount, RD$16.8 million would be for the construction of the wall and the other RD$2.7 million was for work on the dam.

The rush to sign contracts during the transition period at the State-owned power companies CDEEE, was also denounced by the local media.

Share / Recommend this article: FacebookFacebook Digg thisDigg this del.icio.usdel.icio.us TechnoratiTechnorati YahooYahoo Facebook
COMMENTS
10 comment(s)
Written by: Slick, 31 Aug 2012 8:46 AM
From: Dominican Republic
Now let's see if he gets prosecuted.
Written by: Ricardolito, 31 Aug 2012 8:47 AM
From: Dominican Republic, calle A.Portes
What is the issue,,if there were proper tender documents and open tendering and the person or company with the best tender won and was awarded the contract ,,,does the entire country have to stop because of a transition period If normal business continues and there are no irregularities, what is the problem ..or do we go into a cocoon for a few months .
Written by: juanb, 31 Aug 2012 9:09 AM
From: Dominican Republic


Well.....LaDeeDah LaDeeDah
Written by: zooma, 31 Aug 2012 9:27 AM
From: United States


Let's us be realistic and worldly. No matter what culture, country, political persuasion; officials and government agencies use the fog of government transition to push through agendas that favor them and cronies; agendas that would otherwise be placed on the back burner or placed in file 13 through normal government processes.

Why should it be no different here ?

In some but no all cases there is a benefit to it.

Written by: josean, 31 Aug 2012 9:32 AM
From: United States, Fighting the Dictatorship of the Narco PLD Mafia; Guillermo Moreno President 2016


All work in public offices slowed down like molasses during the election for months for the general public while the taxpayer paid public "servants" were out campaigning during work hours. Yet the hopefully to be indicted criminals did not miss a beat in putting their hands in the cookie jar!




Written by: josean, 31 Aug 2012 9:35 AM
From: United States, Fighting the Dictatorship of the Narco PLD Mafia; Guillermo Moreno President 2016

Saint Celso may have some "SPLAING" to do as well!


Written by: hernandez5482, 31 Aug 2012 11:01 AM
From: United States, Vivir sin Patria, es lo mismo que vivir sin Honor.
The problem is that we lack oversight, there should be an investigation and if the contract was issued without following proper procedure then those involved should be punished.
Written by: MrThelmoAlmeydaRancier, 31 Aug 2012 5:14 PM
From: United States, NJ
The problem lies on the non existing of govrnment's functionaries. If they had such a department that follows thru regadrless changes of guards.This stems from (Capital Project allocations) to
(Contract Compliance) The latter assures the project does not have short cuts and follows exactly the propper Engineer's Standards & Guide Lines,with (starting & finishing project dates), non of these would had occurred.

As hernandez5482 points out above.
Written by: Ricardolito, 31 Aug 2012 9:00 PM
From: Dominican Republic, calle A.Portes
Departments do not stop work in the interregnum ,,there are proper guidleines for tendering in place and it is open tendering so the results can be seen .There was a special notice this time from Danilo that all officers should continue their work as normal in the interregnum.
If any one has a complaint with the tender process you simply go to the audit office . There are very few times any minister can interfere with the process and these times are outlined in the law and include things like the proclaiming of a national emergancy
Written by: bernies, 1 Sep 2012 10:47 AM
From: United States, key west fl
Hey guys sometimes the justice works if not lets just look at the case of the selling of ASTER to a company that paid 27,000,000.00USD for it when the central had it list for 42 millions USD, well Satel and Telemicro filed a complaint because they were left out of this deal and because the amount that was sold for it was way to lower than what it actually worth. Just last year the central bank expend 17 millions USD in changing from Analog to Digital. But to all of us surprice the court gave a vedict cancelling the sale and for it to be resumit it for other companies to participate in biding. So if something was done wrong on these contract then someone has to file a complaint against it and let the court to decide if they were impropers or legal contracts, that is all I have to say to this.
Post Your Comment | Not a member? Create your account | Lost your password?
Write your opinion here. Please keep your comment relevant to this article. Please note that any comments which contain offensive language or discriminatory expressions may be edited/removed.
You must log in to post a comment:
Username Password